Active Projects
12
$847M total contract value
On-Schedule Projects
8
67% vs industry avg 42%
Safety Incidents MTD
0
847 work hours since LTI
Cost Variance
+2.1%
Over budget β monitoring
π€ AI Agent Status
13 construction AI agents across project, site, and procurement
Schedule Intelligence2 delays detected
Safety Monitor3 active alerts
Cost Control+2.1% variance
RFI Processor12 RFIs in queue
Quality Inspection4 sign-offs today
Procurement AI3 POs raised today
π‘ Live Site Intelligence Feed
Real-time AI monitoring across all projects and sites
Priority Project Status
PRJ-2024-0001
CRITICALRiverside Tower β 24-floor RC Frame
β AI: Concrete pour delayed 8 days β crane breakdown Level 14
PRJ-2024-0007
AT RISKM-40 Motorway Extension β 12km
AI: Bitumen supply chain 3-week delay β re-sequence recommended
PRJ-2024-0011
ON TRACKSt. Andrews Hospital Wing β $84M
AI: All milestones met Β· next: structural steel week 27
Why ConstructionOS
π
Schedule Overruns
90% of construction projects finish late. The average delay is 20% beyond planned duration. ConstructionOS detects schedule risks 14 days before they become critical β while there is still time to act.
β Safety Incidents
Construction accounts for 20% of all workplace fatalities despite being 6% of the workforce. The Safety Monitor analyses site footage, toolbox talk records, and near-miss reports to prevent incidents before they occur.
π° Cost Overruns
Average construction project is 66% over budget (McKinsey). The Cost Control Agent tracks earned value, flags cost variances, and predicts final cost at completion before the overrun becomes irreversible.
Active
12
Critical
2
At Risk
4
On Track
6
TCV
$847M
All Active Projects
PRJ-2024-0001
CRITICALRiverside Tower Β· 24-floor RC
PRJ-2024-0003
DELAYEDGreenfields Residential Β· 240 units
PRJ-2024-0007
AT RISKM-40 Motorway Extension Β· 12km
PRJ-2024-0011
ON TRACKSt. Andrews Hospital Wing
PRJ-2024-0014
ON TRACKCentral Business Park Β· Phase 2
PRJ-2024-0018
AT RISKSolar Farm Β· 150MW Β· Site prep
Project Detail β PRJ-2024-0001
Riverside Tower β 24-floor Residential
RC Frame Β· Started Nov 2024 Β· Target complete: May 2026
Contract Value
$142,000,000
Schedule Status
-8 days (crane)
Cost Variance (CPI)
0.94 (-6%)
Completion (SPI)
0.97 Β· 53%
β AI Flags
1. Tower crane TC-2 breakdown at Level 14 β 8-day concrete pour delay
2. Delay cascades to structural steel β knock-on +12 working days
3. Final completion risk: +3 weeks if crane not repaired by May 22
4. EAC revised to $148.2M (+4.4%) β AI cost-to-complete forecast
2. Delay cascades to structural steel β knock-on +12 working days
3. Final completion risk: +3 weeks if crane not repaired by May 22
4. EAC revised to $148.2M (+4.4%) β AI cost-to-complete forecast
Total Agents
13
Actions Today
847
Safety Flags
3
Schedule Alerts
2
Project Intelligence Agents
Schedule Intelligence
Analyses programme using critical path method, resource-loaded schedules, and dependency chains. Detects delay risks 14 days early. Suggests mitigation sequences to recover float.
Running Β· 2 delays
ReAct + CPMCost Control Agent
Earned value management: tracks CPI, SPI, EAC, TCPI in real time. Flags cost variances above threshold. Predicts final cost at completion using regression on similar past projects.
Running Β· +2.1% var
Reflection + EVMRFI & Submittal Processor
Analyses RFIs against contract drawings and specs. Generates draft responses with clause citations. Tracks submittal register, review cycles, and approval status.
Running Β· 12 RFIs
Reflection + RAGSafety & Quality Agents
Safety Monitor
Analyses site induction records, toolbox talks, near-miss reports, and permit-to-work compliance. Flags non-compliant activities in real time. Integrates with IoT wearables and camera feeds.
Running Β· 3 alerts
ReAct + VisionQuality Inspection AI
Generates ITPs (Inspection and Test Plans), tracks NCRs (Non-Conformance Reports), and manages hold/witness point compliance. Photo evidence AI analysis.
Running Β· 4 sign-offs
Reflection + VisionBIM Clash Detection
Integrates with Revit and Navisworks. Detects hard and soft clashes between structural, MEP, and architectural models. Generates clash reports with priority ranking and resolution suggestions.
Processing Β· 14 clashes
Multi-Agent + BIMSite Operations Agents
Procurement AI
Matches material requirements to project programme. Raises POs ahead of delivery need. Tracks supply chain disruptions and recommends alternative sourcing when lead times are at risk.
Running Β· 3 POs raised
Planning + Supply ChainLabour Intelligence
Tracks site headcount vs programme requirements. Flags trades shortfalls 2 weeks ahead. Manages subcontractor performance scores, payment milestones, and attendance records.
Running Β· 284 workers
ReAct + ForecastingDocument Control AI
Manages drawing revisions, transmittal logs, and contractual correspondence. Flags superseded documents, ensures latest-revision-only usage, and tracks contractual notice deadlines.
Idle Β· all current
Sequential + RegistryActive Alerts
3
Immediate action
Days Since LTI
847
Lost Time Injury free
Safety Walks (AI)
47
Daily AI site review
Near Misses (MTD)
2
Both investigated
Active Safety Alerts
β Working at Height β No Harness Detected Β· PRJ-0001 Level 12
CRITICALCamera feed AI detected worker at Level 12 parapet without fall arrest harness. Zone: grid C4-D5. Time: 19:41. Worker ID: unknown (no face recognition β GDPR compliant). Site supervisor alerted immediately. Work zone should be halted until compliance confirmed.
β Permit to Work Expired β Hot Works Β· PRJ-0001 Level 8
HIGHHot works permit #PTW-0847 expired at 18:00. Welding activity detected via smoke sensor at Level 8 at 19:15 β 75 minutes after permit expiry. Subcontractor: Apex Steelworks. Continuation without valid permit is contractual breach and regulatory violation.
π Induction Overdue β 4 Workers Β· PRJ-0007 Site
MEDIUM4 new subcontractor workers on PRJ-0007 site have not completed site induction within required 24-hour window. Subcontractor: Delta Groundworks. Site access should be restricted until induction complete.
Critical Path Tasks
247
Delays Detected
2
14 days advance warning
Float Saved
34 days
AI recovery sequences
Forecast Accuracy
89%
π
Schedule Analysis β PRJ-2024-0001
Critical path impact of Level 14 crane breakdown
ANALYSE β Critical path recalculated post-crane event
IMPACT β L14 concrete: -8 working days
CASCADE β Structural steel: knocked on -12 days
OPTIONS β 3 recovery sequences generated
OPT1: Weekend concrete pours (+$84K cost)
OPT2: Rented mobile crane (+$47K/wk)
OPT3: Re-sequence floors 15-17 parallel
RECMD β OPT2 + OPT3 combined: recover 10 days
IMPACT β L14 concrete: -8 working days
CASCADE β Structural steel: knocked on -12 days
OPTIONS β 3 recovery sequences generated
OPT1: Weekend concrete pours (+$84K cost)
OPT2: Rented mobile crane (+$47K/wk)
OPT3: Re-sequence floors 15-17 parallel
RECMD β OPT2 + OPT3 combined: recover 10 days
AI Recommendation: Mobilise rental crane within 3 days AND re-sequence Levels 15-17 to run concurrently. Net recovery: 10 of 12 days. Residual delay: 2 days β within contractual EOT allowance for unforeseen plant failure.
π Programme Health β All Projects
SPI (Schedule Performance Index) across 12 active projects
PRJ-0001 Β· Riverside Tower0.97
PRJ-0003 Β· Greenfields0.88
PRJ-0007 Β· M-40 Motorway0.94
PRJ-0011 Β· St Andrews1.02
PRJ-0014 Β· Business Park1.00
Total Budgeted Value
$847M
Overall CPI
0.96
Below 1.0 = over budget
EAC (all projects)
$881M
Forecast at completion
Variance to Budget
+$34M
+4.0% over budget forecast
π° Earned Value β PRJ-2024-0001
Cost performance vs plan Β· AI forecast to completion
Planned Value (PV)$74.2M
Earned Value (EV)$71.9M
Actual Cost (AC)$76.5M
Cost Performance Index (CPI)0.94
Schedule Performance Index (SPI)0.97
EAC (AI forecast)$148.2M (+4.4%)
β οΈ Cost Variance Drivers
AI-identified root causes of cost overrun
Crane breakdown repair + rental: +$284K direct + $47K/week rental. Uninsured portion: $180K.
Concrete price escalation: Ready-mix +12% above bill of quantities rate since contract award. Change order required.
Rework β Level 9 formwork: Defective formwork resulted in re-pour. Subcontractor liable β NCR issued. Recovery: $180K via retention.
Value engineering saving: Alternative precast staircase saved $340K vs in-situ design. Net variance positive on this line item.
RFIs Open
12
AI Draft Response
94%
Accepted by engineer
Avg Response Time
4h
vs 3 days manual
Submittals Tracking
284
π RFI Processing β How It Works
The RFI Agent reads each Request for Information against the contract drawings, specifications, and schedules. It extracts the technical question, retrieves relevant drawing revisions and specification clauses from the document control RAG corpus, and generates a draft response with clause citations. For complex RFIs requiring engineer's professional judgment, the draft is flagged for senior review. All RFI responses include contractual basis, relevant drawing/spec references, and cost/time implications if any. Average engineer review time: 15 minutes vs 3 days manual.
ITPs Completed
847
NCRs Open
4
Hold Points
3
Awaiting engineer
Photo Evidence
2,847
β
Quality Management System
Quality Inspection AI manages the full ITP lifecycle: generates inspection and test plans from specification requirements, tracks hold/witness/review points, and uses vision AI to analyse photo evidence of completed work. NCR detection: AI flags deviations from specification in inspection photos (e.g., rebar spacing, concrete surface finish, weld quality). All NCRs tracked to closure with root cause analysis. Documents fully ISO 9001 compliant quality management trail.
POs Raised Today
3
Supply Chain Risks
2
Cost Savings AI
$284K
Lead Times Monitored
847
π¦ AI Procurement Intelligence
The Procurement Agent analyses project programme to identify material requirements 6β8 weeks ahead of need date. Monitors supplier lead times and flags shortfalls before they become critical path events. Bitumen delay (PRJ-0007): detected 3 weeks before impact. Three alternative suppliers identified with comparable spec at +2% cost premium. Recommendation: split order across two suppliers to de-risk single-source dependency. Cost saving from AI-negotiated bulk buys: $284K YTD across all projects.
Workers On Site
284
Trades Shortfalls
2
Next 2 weeks
Productivity Index
0.92
Subcontractors
18
π· Labour Intelligence
Labour Agent tracks site headcount vs programme resource requirement curve for every trade. Forecasts shortfalls 2 weeks ahead using programme look-ahead + subcontractor resource returns. Current flags: Electrical (PRJ-0001, Week 32) β 4 sparks required, subcontractor confirmed only 2. Recommended action: engage additional electrical sub. Structural steel (PRJ-0011, Week 28) β 6 ironworkers needed β ahead of schedule milestone. Productivity index tracks actual progress vs planned man-hours to identify low-output activities early.
Drawings Managed
4,821
Current Revision
100%
Superseded in Use
0
Transmittals
847
π Document Control AI
Document Control Agent manages 4,821 project documents across drawings, specifications, submittals, RFIs, and correspondence. Key function: superseded drawing detection β alerts when site teams are referencing an outdated revision. Automated transmittal register ensures all design changes are formally issued and acknowledged. Contractual notice tracking: monitors notice deadlines under NEC/JCT/FIDIC contract forms to protect time and cost entitlements. AI parsing of architect's instructions, variation orders, and engineer's certificates for automated cost register updates.
Agents Active
13
Actions/Day
847
Safety Events
3
Schedule Alerts
2
π‘ Live Agent Trace
All AI decisions logged β ISO 19650 compliant
π‘ Construction AI Governance
Why every AI output is advisory β not autonomous
Safety decisions β always human: AI flags safety hazards but never issues stop-work orders autonomously. Site supervisor confirms and acts. Life-safety decisions require human judgment.
Contractual actions β engineer approved: RFI responses, variation orders, and NCRs require engineer sign-off. AI generates drafts, humans approve. All actions legally binding only with authorised signature.
ISO 19650 BIM compliance: All document management actions logged per ISO 19650 Common Data Environment requirements. Full audit trail for employer information requirements.